Dear Tnsys users,
I want to simulate an AHU building integrated using type 112b. Control signal of type 112b is: The fan (type 112b) is to be ON if the relative humidity of a zone is greater than 70%.
When I run simulation, it gets blocked at a given time as shawn in figure below:
Where does the problem come from ?
Thanks in advance
Ismail
--
************************************************
Ismail OUHALLOU
Green building & Sustainability consultant
Morocco
P:+212 620 548 116
F:+212 522 326 440