[Date Prev][Date Next][Thread Prev][Thread Next][Date Index][Thread Index]

Re: [TRNSYS-users] how to control HVAC ?



Ahmad,

 I would recommend that you download the tutorial called "Temperature Level Control from Energy Rate Control " at:


http://sel.me.wisc.edu/trnsys/downloads/tutorials_and_examples/tutex17.htm


or if you are using v16


http://sel.me.wisc.edu/trnsys/downloads/tutorials_and_examples/tutex.htm


It will explain some of the differences between calculating a building load and simulating the performance of HVAC systems. It will also lead you through an example of converting a load computation simulation into an HVAC system simulation.

kind regards,

 David




On 02/07/2017 13:34, ahmad abbasian via TRNSYS-users wrote:

Dear Jeff

Thank you for your guiding. I have simulated my HVAC system at nominal condition, alone not using the building model. Now I'm going to use this system connected to a building. Now my question is how should I match the HVAC cooling production to the building load which is transient? should I control the temperature and humidity also or just the flow rate should be controlled to meet the load? 

I couldn't find a similar example in TRNSYS examples. Could you send me an example in case of having some please?

Thank you

..............................................................................................
Ahmad abbasianzadeh
Solar energy Researcher
Harrisburg, Pensylvania


 

From: TRNSYS-users <trnsys-users-bounces@lists.onebuilding.org> on behalf of Jeff Thornton via TRNSYS-users <trnsys-users@lists.onebuilding.org>
Sent: Tuesday, February 7, 2017 7:09:11 AM
To: trnsys-users@lists.onebuilding.org
Subject: Re: [TRNSYS-users] how to control HVAC ?
 

Ahmad,

There are literally hundreds of ways to control the temperature and humidity in a space.  I would suggest you do some reading to figure out a common HVAC system given your climate and type of building - then you can begin to replicate that system in TRNSYS. 

 

Jeff

 

---
Jeff Thornton
President - TESS LLC
22 N. Carroll Street, Madison WI USA 53703
Office: (608) 274-2577  Fax: (608) 278-1475
www.tess-inc.com
E-Mail: thornton@tess-inc.com

On 02/07/2017 12:08 pm, ahmad abbasian via TRNSYS-users wrote:

Hello

I'm simulating a solar assisted coolig system for a building. The building cooling load is transient. so how the HVAC system should be controlled to cover the building load? I guess that the supply air temperature and humidity ratio should be constant ( a value in the comfort region ) and the air flow rate should be controlled using a variable speed fan to cover the cooling load. Is it right? any better idea?

Also I don't know how the control system should be? should I use a thermostat? 

If any one can send me an example it will be very useful for me to learn

Thank you 

 

..............................................................................................
Ahmad abbasianzadeh
master of energy systems engineering
Solar energy Researcher
Harrisburg, Pensylvania
 
 
 

_______________________________________________
TRNSYS-users mailing list
TRNSYS-users@lists.onebuilding.org
http://lists.onebuilding.org/listinfo.cgi/trnsys-users-onebuilding.org


_______________________________________________
TRNSYS-users mailing list
TRNSYS-users@lists.onebuilding.org
http://lists.onebuilding.org/listinfo.cgi/trnsys-users-onebuilding.org

-- 
***************************
David BRADLEY
Principal
Thermal Energy Systems Specialists, LLC
22 North Carroll Street - suite 370
Madison, WI  53703 USA

P:+1.608.274.2577
F:+1.608.278.1475
d.bradley@tess-inc.com

http://www.tess-inc.com
http://www.trnsys.com