Massimo,
  Assuming that you have a 1-year weather data file the best way to accomplish that is to set your simulation start time to an hour of the year near the end of december (8592, for example will set the simulation start time to one week before the end of december). You then set your simulation stop time to 17520. If you think that you need a longer warmup period (for instance if you are doing a building and ground coupling then you can simply run a multi year simulation (start time 0, end time 17520 26289, etc.)
kind regards,
 David


On 04/27/2016 08:21, massimo truant wrote:

 

Good afternoon,

My question is very simple: is possible to assign to trnsys a period of time of pre-simulation before the real simulation (just to fix the data of the iteration)?

 

Thanks to all

 

Inviato da Posta per Windows 10

 



_______________________________________________
TRNSYS-users mailing list
TRNSYS-users@lists.onebuilding.org
http://lists.onebuilding.org/listinfo.cgi/trnsys-users-onebuilding.org

-- 
***************************
David BRADLEY
Principal
Thermal Energy Systems Specialists, LLC
22 North Carroll Street - suite 370
Madison, WI  53703 USA

P:+1.608.274.2577
F:+1.608.278.1475
d.bradley@tess-inc.com

http://www.tess-inc.com
http://www.trnsys.com