Re: [TRNSYS-users] Calling EES Message 129



Mattias,
  The 4th parameter of Type66 asks for the number of outputs that are expected to be returned by EES. If EES is putting more outputs onto the clipboard than are expected then the error you mention would be triggered. You say that you get this error using compressor.ees but does the error come when you are calling EES from the Calling EES.tpf project or when you call compressor.ees from your own project. If the value of Type66's 4th parameter and the number of items being placed on the clipboard in the $Export 'CLIPBOARD' line in the EES file match then please send your *.tpf and the *.ees file (as well as any other files needed in order to run the project) to your distributor for assistance and debugging.
kind regards,
 David


On 3/13/2015 07:23, Mattias Ericsson wrote:

I am trying to call EES for every time step. The link seems to work since EES is opened but then it closes and I get the TRNSYS Error 129:

 

“TRNSYS Message    129 : The referenced Unit has tried to set an Output value higher than the number of Outputs that the Type reserved for itself.”

 

I get the same Message when I use my own EES-file or the sample file compressor.ees.

 

Does anyone have a clue what the problem could be?

 

Best regards

 

Mattias Ericsson



_______________________________________________
TRNSYS-users mailing list
TRNSYS-users@lists.onebuilding.org
http://lists.onebuilding.org/listinfo.cgi/trnsys-users-onebuilding.org

-- 
***************************
David BRADLEY
Principal
Thermal Energy Systems Specialists, LLC
22 North Carroll Street - suite 370
Madison, WI  53703 USA

P:+1.608.274.2577
F:+1.608.278.1475
d.bradley@tess-inc.com

http://www.tess-inc.com
http://www.trnsys.com