Hi everybody!
 
I have a question that maybe doesn´t have answer...
 
Is it possible to predict any result in trnsys?
 
I have the demand of a building (a profile) and I want to satisfy this demand using a fixed producer (could be microcogeneration) with a deposit to storage energy not used and make use of it when there is demand. What I´d need to know is if there is any strategy to know the size of this fixed producer (for example...5-10-15 kW....) if I limit the size of the storage (for example....5-10-15 kW....) or viceversa, with a fixed producer if I could know the optimal size of the storage, I mean without studying the whole simulation, without simulating and analyzing the evolution of the plot. I want to know if there is any relationship between these factors (profile load, fixed producer and size storage).
 
Any answer will be welcome!
 
Thanks!
 
Best regards,
 
Maria