Dear Nguan,

If you use that schedules applied to people gains, you will obtain :

    - 10 persons during Workday and none otherwise in the case of 10*WORKDAY + 0 schedule
    - 10 persons all the time and one more during Workday - so 11 persons during Workday and 10 otherwise, in the case of 1*WORKDAY + 10 schedule

Both cases are completely different.

Best regards

www.itf.biz
www.itf.biz
Adrien JEZEQUEL
Simulations Thermiques Dynamiques
ITF
87, Avenue de Chambéry
73230 St Alban Leysse
FRANCE
Phone :
Fax :
Mail:
+33(0) 479 750 029
+33(0) 479 852 122
a.jezequel@itf.biz
Afin de contribuer au respect de l'environnement, merci de n'imprimer cet e-mail que si nécessaire
Please, consider our environmental responsability before printing this email


#TEO NGUAN TECK# a écrit :

Hi All,

 

I am using schedule for my simulation and I would like to know if my interpretation is correct:

 

For example, I need to include 10 person in my zone during office hours:

 

I am currently using:       10*WORKDAY + 0

 

Would it be the same if I were to use 1*WORKDAY + 10?

 

Any help is deeply appreciated.

 

Nguan Teck

NTU, Singapore


---------------------------------------------------------------------------------------
Orange vous informe que cet e-mail a été contrôlé par l'anti-virus mail.
Aucun virus connu à ce jour par nos services n'a été détecté.



_______________________________________________ TRNSYS-users mailing list TRNSYS-users@cae.wisc.edu https://www-old.cae.wisc.edu/mailman/listinfo/trnsys-users