Dear TRNSYS
Users
I have just
discovered there is a time step in TRNBUILD which is different from the
time step in the Studio (deck).
I had run a lot of simulations with a
TRNBUILD time step of 1 hour and a Studio time
step really lower (30 seconds, 1 minute, 5
minutes ) . These simulations
seemed quite good and worked well if we put an Input Value Recall
(Type 93) between the Building outputs and some other
components.
I have now changed
the time step in TRNBUILD (0.1 hour => I couldn't go lower) and changed the
Studio time step to 0.1 hour.
I can see
differences, but they are not big : less than 2% for a total consumption of the
year.
The problem is
that I am studying strategies of heating regulations. So, I need short time steps to see if my regulation
strategy is good.
I have 2 questions
:
- Do you think
my simulations already run with different time steps between TRNBUILD and the
Studio are wrong ? not realist
?
- If the time steps
of the Studio is lower than the TRNBUILD time step, what information / instructions
are given by the studio to TRNBUILD ?
For exemple I have
calculated with the Studio every
minute the air temperature to blow into a room in the Studio, the TRNBUILD time
step is 1h : what is the air temperature used in TRNBUILD : the mean of the
temperatures calculated every minutes ? only the temperature calculated at 60
minutes ? or an other one ?
Thank you for your
help
Kind
regards,